Construction
Major construction projects for 2025 in Barrhaven East, including road resurfacing, sidewalk rebuilds, and other work which may require road cuts, lane closures, or adjustments in traffic, pedestrian, and cyclist patterns are listed below. Some of the projects listed below may also be carried over or delayed from previous years.
Minor works, projects completed in previous years, fibre optic installations, and projects in other wards are not listed.
Projects are sorted by start date.
New pedestrian crossover
Stoneway/Forest Gate (east)
July and August, dates to be determined
LAST KNOWN STATUS: NOT STARTED
New pedestrian crossover with beacons to replace the existing school crossing on the east side of the intersection (crossing guard to be retained).
New raised pedestrian crossover
Paul Métivier/Beatrice
July and August, dates to be determined
LAST KNOWN STATUS: NOT STARTED
New raised pedestrian crossover with beacons to replace the existing school crossing on the west side of the intersection (crossing guard to be retained).
Multi-use path resurfacing
Greenbank through the Greenbelt
3 July 2025 to late-August
LAST KNOWN STATUS: IN PROGRESS
Asphalt resurfacing along entire pathway between West Hunt Club and Fallowfield. During construction, the pathway will be CLOSED to all users. A detour route in the shoulder of Greenbank Road was considered, but setting up the barriers would have cost more than the project itself.
The resurfacing project will buy us five to 10 years to work on a proper redesign and upgrade of the pathway with the NCC.
Natural gas substation
Earl Mulligan/Woodroffe
June to July
LAST KNOWN STATUS: COMPLETE
Enbridge will be replacing natural gas infrastructure on the north side of Earl Mulligan near Woodroffe. During the works, traffic entering Earl Mulligan will be diverted to the centre lane, while traffic exiting Earl Mulligan will be reduced to one left turn lane. Traffic impacts are expected to be limited to 9:00 am to 3:00 pm.
Sewer relocation
Leikin Drive, between Merivale and Beckstead
20 May 2025 to 11 August 2025 (extended from 20 June)
LAST KNOWN STATUS: IN PROGRESS
Relocation of a deep underground sewer to facilitate future development of the sortation facility. Leikin Drive between Merivale and Beckstead will be fully CLOSED, with a detour route via Beckstead for traffic to/from Merivale.
Sidewalk repairs
Chapman Mills, north side, from Clearbrook to Meadgate
Dates to be confirmed
LAST KNOWN STATUS: NOT STARTED
Full rebuild of sidewalks on the north side of Chapman Mills from Clearbrook to Meadgate. Temporary street parking restrictions may apply.
Infrastructure connection (private project)
Woodroffe/Deerfox-Stoneway
14 August 2024 to TBD
LAST KNOWN STATUS: DELAYED
Overnight construction at the intersection of Woodroffe/Deerfox-Stoneway to allow for a new water and sanitary connection to the commercial properties on the west side of Woodroffe. No closures expected, but lane reductions may be necessary to accommodate the works.
Road resurfacing
Prince of Wales between Rocky Hill and Lodge Road
Dates to be confirmed
LAST KNOWN STATUS: TBD
Prince of Wales Drive was resurfaced in 2023 between Lodge Road and Bankfield. A short section north of Lodge Road was due to be resurfaced but was delayed to accommodate road cuts for the police station construction.
Resurfacing will be completed at a future date, after the police station is complete.